The Objective

The Team Created 3D architecture and structure layout in Revit MEP and allocate mechanical equipment with connection for a clash free model.Technology/Software Used



  • A detailed plant room with all the spatial information, equipment and connections had to be developed from general arrangement drawings and a set of pdf files with manufacturing details of the MEP equipment.
  • The process henceforth involved clash detection, reporting and resolutions. Finally clash free models, rendered images and shop drawings had to be delivered in a time span of 3 Months.

Engineering Solution

  • MEP designs and general arrangement drawings were thoroughly examined
  • Basic 3D architecture and structure layout was created in Revit MEP
  • Mechanical equipment with detailed connections and well arranged clash free model as per provided inputs was prepared
  • In addition to Revit MEP Plant rooms and shop drawings, sheet setup and 3D rendering as required was also developed and handed over to client


  • The project was successfully executed and handed over within the specified time frame of 3 months.
  • Initially the contract was on project basis. As client was satisfied with the quality produced, he has opted for full time resource business model and a long term partnership was built.

Thanks for reading!

Please enjoy a limited number of articles over the next 30 days.

For total access log in to your The BIM Hub account. Or register now, it's free.

Register Sign in


You might also like