LOD 300 Modelling According to AIA Standards for a Reputed Public Park in USA

Posted by

Documents

Document downloads are only available to registered members. Click here to sign in.

If you have not created an account yet, then please sign up first.

The Client

Industry: Construction and Engineering 
Location: California, USA

The Objective

Creation of information rich, intelligent BIM with architectural, structural and MEP details for a 6 storied building in California

The Solution

The drawings and building details were converted into intelligent BIM with LOD 300, for material take offs, project coordination, scheduling and clash detection.

Technology/Software Used

Revit, Navisworks

A California based construction and engineering company approached Hi-Tech with a project, to create information rich intelligent BIM for a residence Inn – A 6 storied building with a basement for car parking.

The construction area, spread across 10,500 sq. ft. The client wanted BIM with LOD 300, for architectural, MEP and structural disciplines. The primary reason of outsourcing BIM services was to avail detailed documentation, to detect and mitigate clashes at an early stage and make the construction process efficient and cost effective.

Challenges

  • The structural drafts and specifications were missing in the input files provided by the client
  • On request, these details were provided however, the process consumed a lot of time
  • The side cutting fields at the basement were problematic, where the dimensions and survey points were not matching

Engineering Solution

Advertisement
  • Inputs received as .PDF files, were successfully converted into BIM for architectural and MEP disciplines
  • Inputs for structural discipline were missing; hence, the details were generated based on engineering assumptions. Waiting for the inputs from client, could have delayed the project.
  • At a later stage when the missing information arrived, it was found that the engineering assumptions were 90% accurate. Required iterations were done in the 3D Revit model.
  • A Building information model with architectural, structural and MEP details was ready.
  • Finally, the model was analyzed, for coordination and clash detection. All the clashes were detected and mitigated.
  • Information rich, intelligent BIM with LOD 300 for effective material take offs, project coordination, and scheduling was prepared.

Benefits

  • Engineering assumptions made by the BIM experts, for the missing structural data, were 90% accurate.
  • Even after the delays in receiving structural details and input files from the client, the project was successfully executed within the set time frame of 6 weeks.
  • Clash detection helped clients detect and mitigate clashes at an early stage, and save the massive costs of mitigating these clashes at the time of actual construction.
  • The material takes offs, and project scheduling estimates provided, reduced the overall time and cost of construction, and made the process seamless, coordinated and error free.

Thanks for reading!

Please enjoy a limited number of articles over the next 30 days.

Free sign up for total access.

Already have an account? Then please sign in.

Posted by

Gaurang Trivedi

Gaurang Trivedi is engineering consultant at TrueCADD. Besides, donning multiple hats, as a website manager and marketing in charge, he also oversees the editorial content, coordinating and managing the website, its news sections, blogs and social media promotions as well. Learn more

blog comments powered by Disqus